Avon WWTF, Edwards WWTF, Avon WTF

$4,967,950 Owner: Eagle River Water & Sanitation Engineer: Brown and Caldwell Schedule: 05/2007

This $5 mil contract required a greatly accelerated construction schedule for improvements to three existing treatment plants (2 wastewater, 1 water) in Avon and Edwards, Co. The contract required 15 of 16 tasks (valued at $4mil) to be completed in a 5 month performance period. This included submittal review, procurement, and installation of major mechanical systems including odor control, chemical feed, polymer feed, RDT, ATAD, aeration basin equipment, nitrification, scrubbers, emergency generator, clear well improvements, and other structural modifications. UV building and UV system required an 8 month completion period.