Sandhill Reservoir Outlet Works Rehabilitation

$515,058 Owner: Platte Valley Irrigation Company Engineer: Frachetti Engineering Schedule: 05/30/2014

The project was an emergency rehabilitation for the existing reservoir outlet works with the Sandhill Reservoir near Fort Lupton, CO. Design build project with Aslan Construction as the Construction Manager at Risk. Improvements included slip lining 530 LF of the existing 48” RCP outfall line with new 43” OD Hobas fiberglass pipe, a new intake structure with a 48”slide gate for flow control, and a new electrical gate actuator and stem extension grade beam were also constructed. The joint efforts of the engineer and Aslan saved the Owner approximately $180,000.