Silt Pump Modernization

$3,826,375 Owner: Bureau of Reclamation Engineer: Bureau of Reclamation Schedule: 10/12/2016 - 05/19/2018

Rehabilitation of the Silt pumping plant, including removal of four existing pumping units, replacement of four pumps while refurbishing four motor units. The new pumps and refurbished motors will be reinstalled and have new electrical and SCADA connections. The hydraulic power unit and the vacuum priming systems associated with the pumping units will be removed and replaced. The pump replacement will be coordinated with the canal company to maintain water flow for the farmers. An oil/water precast separator unit will also be installed and minor site work and yard piping will be performed.